Delivered an integrated multi discipline engineering design for Specialty chemical facility comprising 270+ piping lines across critical process and utility with intelligent 3D model of all facilities.

6067 - MEE PLANT PROJECT — Project

Owner

AARTI INDUSTRIES LIMITED.

Client

AARTI INDUSTRIES LIMITED.

PMC

--

Location

JAGADIA, INDIA

Project Scope

The Project comprises engineering of Piping systems, intelligent 3D modelling of complete facility, piping stress analysis, Electrical and Instrumentation and Civil & Structural for various process systems of MEE plant along with RO feed tank and Nitric solution feed tank to support safe, reliable, and efficient operation of the facility while ensuring constructability, maintainability, and optimized plant layout.

Development and finalization of engineering deliverables for procurement, fabrication, construction, and commissioning activities.

Intelligent 3D modelling covering the complete process unit and RO feed tank and Nitric solution tank.

Performed pipe stress analysis considering Thermal expansion and sustained loads, Operating conditions and flexibility requirements.

Major facilities include MEE plant along with dedicated RO feed tank and Nitric solution feed tank.

Engineering activities include piping routing, piping layout development, critical line stress analysis, utility integration and multidisciplinary coordination.

Intelligent 3D model utilized for equipment positioning, routing optimization, clash detection, constructability review, and interdisciplinary coordination.

Civil and Structural engineering G+4 process structure and RO & Nitric solution feed tank area, Equipment foundations, Interconnecting racks and pipe supports.

Electric and Instrumentation engineering for MEE plant and RO, Nitric solution feed tank area.

Engineering execution focused on safe operation, optimized plant layout, maintainability, accessibility, structural integrity, and efficient project execution.

Deliverables developed in compliance with applicable engineering standards, codes, and project specifications.

Key Highlights

Successfully executed detail engineering of Piping systems, Intelligent 3D modeling and Piping Stress analysis of facility with 270+ No. of lines, 40 No. of equipment and plot area 450 m2.

Engineered process facility MEE plant G+4 with height 22 m. and Footprint area 11m × 16m.